Mining projects are rarely approved in one leap. They move through a ladder of increasingly detailed studies, each designed to reduce uncertainty before more money is spent. These stages are known as the scoping study, the pre-feasibility study and the feasibility study. The terms are used constantly in the industry, yet they are often confused, or worse, misused to make an early-stage project sound more advanced than it is.
This article explains the differences between the three study stages, what each is meant to achieve and how to decide which one your project needs.
Why Mining Uses Staged Studies
Mine development involves high capital cost, long timelines and geological uncertainty. Staging allows owners to spend small amounts early to test the idea, then increase spending only if results justify it. At each gate, the project is reviewed, and a decision is taken to proceed, change direction or stop. This approach is a core part of risk management in mineral development.
Stage 1: The Scoping Study
Purpose. To determine whether a project has potential and is worth further investment. It is a high-level screening tool.
Data basis. Existing exploration results, limited drilling, preliminary resource estimates and desktop analysis. Assumptions are often based on benchmarks and similar operations.
Content. A conceptual mining method, a simple process flow concept, order-of-magnitude capital and operating costs, a basic financial model and an outline of infrastructure, environmental and social considerations. Several alternative development concepts may be compared.
Accuracy. Low. Capital cost estimates are usually described as accurate to around plus or minus 30 to 50 percent.
Resource classification. May include Inferred resources, with appropriate warnings in disclosure.
Cost and duration. The least expensive and fastest, typically weeks to a few months.
Outcome. A decision on whether to proceed to pre-feasibility, drill more, redesign the concept or stop. In Canada, a similar study is called a Preliminary Economic Assessment (PEA).
Stage 2: The Pre-Feasibility Study
Purpose. To evaluate options in more detail, select a preferred development case and establish whether the project is likely to be viable. It also defines the scope of the feasibility study.
Data basis. Indicated or Measured resources, additional drilling, preliminary metallurgical test work, geotechnical and hydrogeological information, baseline environmental data and initial community engagement.
Content. Evaluation of multiple mining and processing options, trade-off studies, a preliminary mine design and schedule, a defined process flowsheet, infrastructure layouts, more detailed capital and operating cost estimates and a more thorough financial analysis. Ore reserves can be declared at pre-feasibility level if modifying factors are adequately supported.
Accuracy. Moderate, commonly around plus or minus 25 percent.
Cost and duration. Considerably higher than scoping, because it requires drilling, test work and engineering. Typically takes several months to a year.
Outcome. A recommended project configuration, a statement on viability and a plan for the feasibility study. If results are weak, the project may be shelved or restructured.
Stage 3: The Feasibility Study
Purpose. To provide a definitive assessment that supports a final investment decision and project financing. Often called a bankable feasibility study (BFS) or definitive feasibility study (DFS).
Data basis. Mostly Measured and Indicated resources, high-quality drilling, comprehensive metallurgical programmes with variability testing, detailed geotechnical and hydrogeological investigations, completed or advanced environmental and social impact assessment and secured key permits or clear approval pathways.
Content. Detailed mine design and scheduling, fully engineered process plant and infrastructure, equipment selection supported by quotations, a detailed capital and operating cost estimate, project execution plan, risk register, closure plan and a comprehensive financial model with sensitivity analysis.
Accuracy. High, usually plus or minus 10 to 15 percent.
Cost and duration. The most expensive and longest stage, often a year or more.
Outcome. A basis for a final investment decision, financing negotiations and detailed engineering. Lenders usually require independent review of the study.
Side-by-Side Comparison
| Feature | Scoping Study | Pre-Feasibility | Feasibility |
|---|---|---|---|
| Main question | Is it worth studying? | Which option is best and is it viable? | Can we build and finance it? |
| Resource confidence | Inferred allowed | Indicated and Measured | Mostly Indicated and Measured |
| Engineering detail | Conceptual | Preliminary | Detailed |
| Cost accuracy | About ±30–50% | About ±25% | About ±10–15% |
| Reserves | Not declared | Possible | Declared |
| Typical duration | Weeks to months | Months to a year | A year or more |
| Typical use | Screening | Option selection | Financing decision |
These figures are indicative and vary by standard, commodity and company practice.
Which Study Does Your Project Need?
Early-stage discovery with limited drilling. Start with a scoping study. Do not commission a feasibility study without adequate data.
Project with a defined resource and promising scoping results. Move to pre-feasibility, focusing on drilling, metallurgy and options analysis.
Project with strong pre-feasibility results and a clear preferred option. Proceed to feasibility, while advancing permitting, community agreements and financing discussions.
Small-scale operations. A simplified combined study may be adequate, but should still address geology, mining, processing, economics, environment and legal matters.
Common Misuse of Terms
Calling a scoping study a feasibility study. This misleads investors and may violate disclosure rules for listed companies.
Using “bankable” loosely. A study is bankable only if lenders accept it. This depends on data quality, qualified authors, realistic assumptions and independent review.
Mixing resource and reserve language. Reserves can only be declared where modifying factors have been properly assessed.
Skipping stages. Going directly to feasibility on weak data often results in expensive redo work.
Role of Reporting Codes
JORC, NI 43-101 and SAMREC set standards for public reporting of exploration results, resources, reserves and technical studies. They require the involvement of qualified professionals, transparent disclosure of assumptions and clear cautionary statements. Even if you do not plan to list on an exchange, following these standards improves credibility with investors and lenders.
Applying the Stages in Kenya
Kenyan projects face practical considerations at every stage. Scoping studies should realistically assess infrastructure, logistics and fiscal terms under the Mining Act, 2016. Pre-feasibility studies should advance environmental baseline work required by the National Environment Management Authority and include community engagement. Feasibility studies should reflect confirmed permits, water rights, land access and local content commitments. Early attention to these factors prevents late-stage surprises.
Decision Gates Between Stages
Each study ends with a decision gate. After scoping, ask whether the project shows positive value at conservative prices and whether the risks can be reduced through affordable work. After pre-feasibility, ask whether a preferred option is clear, whether resources and reserves are adequate and whether permits and community support appear achievable. After feasibility, ask whether the project can be financed and built within acceptable risk. Documenting gate criteria in advance keeps decisions disciplined and prevents momentum from carrying weak projects forward.
Typical Work Packages at Each Stage
At scoping, work is mainly desktop: data review, conceptual design, benchmarking and a basic model. At pre-feasibility, drilling campaigns, metallurgical test work, geotechnical logging, water studies and environmental baselines begin. At feasibility, work packages deepen into detailed engineering, procurement planning, construction scheduling, completion of the ESIA, community agreements and lender-ready financial modelling.
Spending and Timing Expectations
Spending increases at every stage, with the largest jump between pre-feasibility and feasibility. Owners should plan funding in advance and avoid starting a stage that cannot be completed. A half-finished feasibility study is often worth little to investors, whereas a completed scoping or pre-feasibility study with honest conclusions can attract partners.
Independent Review
Independent technical review is useful at any stage but is especially important for pre-feasibility and feasibility studies that support financing. A reviewer checks the resource estimate, mining assumptions, metallurgical basis, cost estimates and financial model, and identifies gaps. Acting on review comments before approaching lenders saves time later.
Applying the Stages to a Kenyan Example
Imagine a licence holder in western Kenya with surface gold sampling and a few shallow holes. A scoping study would test whether a small open pit and gravity-leach plant could be profitable at conservative prices. If positive, the owner would drill to define Indicated resources, test metallurgy and begin environmental baselines during pre-feasibility. Only after a preferred option emerges, and permits and community agreements are advancing, would the owner fund a full feasibility study. Following this ladder protects capital and builds a record that investors can trust.
Conclusion
Scoping, pre-feasibility and feasibility studies form a progressive path from idea to investment decision. The scoping study screens, the pre-feasibility study selects and the feasibility study confirms. Each requires more data, more engineering and more money, but offers more certainty. Understanding the differences helps project owners choose the right study at the right time, communicate honestly with investors and avoid expensive missteps.
For help determining the right study stage for your project, visit consult.innercoregeoconsultants.co.ke.
This article is general guidance. Accuracy ranges and definitions vary by reporting code and company practice.